Work Item Schedule Status Dates
FIO #1 Upgrade Building Automation System Complete July 9, 2010
FIO #2 Upgrade Fire Alarm System Complete July 9, 2010
FIO #3 Lighting Retrofit Complete August 18, 2009
FIO #4 Water Retrofit Complete July 31, 2009
FIO #5 Shop AHU VAV Conversion Complete May 20, 2010
FIO #6 Boiler Replacement Complete June 25, 2010
FIO #7 Fire Sprinklers on 2nd and 3rd Floors Complete July 9, 2010
FIO #8 Auto Bay Return Air Ductwork Reconfiguration Complete November 25, 2009

 

 Projected dates subject to change.  Please check back regularly for updates.

Last updated: January 19, 2011