Work Item Schedule Status Dates
FIO #1 Upgrade Building Automation System Complete April 5 - Aug 27 , 2010
FIO #2 Lighting Retrofit Complete September 25, 2009
FIO #3 Water Retrofit Complete August 19, 2009
FIO #4 Supplemental Cooling to 1st Floor Computer Lab Complete April 1, 2010

 

 

Projected dates subject to change.  Please check back regularly for updates.

Last updated:  January 19, 2011