Work Item Schedule Status Dates
FIO #1 Upgrade Building Automation System Complete April 16, 2010
FIO #2 Upgrade Fire Alarm System Complete May 28, 2010
FIO #3 Lighting Retrofit Complete October 16, 2009
FIO #4 Water Retrofit Complete August 7, 2009
FIO #5 Constant Volume to VAV AHU Conversion Complete March 12, 2010
FIO #6 Upgrade AHUs Complete March 12, 2010
FIO #7 Chiller Refrigerant Conversion Complete December 23, 2009
FIO #8 2nd Floor Costume Shop Ventilation Complete August 14, 2009

 

 

 

 

 

 

 

 

Projected dates subject to change.  Please check back regularly for updates.

Last updated:  January 19, 2011