Work Item Schedule Status Dates
FIO #1 Upgrade Building Automation System Complete December 1, 2009
FIO #2 Upgrade Fire Alarm System Complete

April 22, 2010

FIO #3 Lighting Retrofit Complete October 30, 2009
FIO #4 Water Retrofit Complete August 3, 2009
FIO #5 Constant Volume Dual Duct to VAV Dual Duct Conversion Complete September 4, 2009
FIO #6 Upgrade AHUs Complete April 8, 2010
FIO #7 Boiler Replacement Complete Nov 9 - June 25, 2010
FIO #8 Chiller Replacement Complete April 14, 2010
FIO #9 Fume Hood Replacement Complete June 21 - Aug 13, 2010
FIO #10 Install New Emergency Generator Complete April 1 - July 14, 2010
FIO #11 Roof Section Repair Complete August 26, 2009
FIO #12 Ceiling Removal Complete July 20, 2009
 FIO #12 Ceiling Replacement Complete October 16, 2009
FIO #13 Pump Replacement Complete December 28, 2009
FIO #14 IAQ DDC Controls Sequence of Operations Deleted March 15 - April 16, 2010
FIO #15 Fire Sprinklers Complete October 16, 2009

Projected dates subject to change.  Please check back regularly for updates.

Last updated:  January 19, 2011